Wednesday, 10 November 2010

Module 1 - loose ends

All modules require timings and costings for the work that has been done. I kept detailed records of the time I spent chapter by chapter.

TIMINGS

Chapter 1 18.5 hours

Chapter 2 16.5 hours

Chapter 3 25 hours

Chapter 4 14.4 hours

Chapter 5 3 hours

Chapter 6 9.5 hours

Chapter 7 31 hours

Chapter 8 22.5 hours

Chapter 9 17.5 hours

Chapter 10 18.5 hours

Chapter 11 39.5 hours

Chapter 12 14 hours

TOTAL 230 hours


I didn't keep careful notes about what things cost. I actually bought very little, with most of what I used coming from my stash, so I have tried to estimate what it has cost.

COSTINGS

Sketchbook 4.50

Paper 5.00

Art materials 7.50

Fabric 50.00

Threads 10.00

TOTAL £77.00

The most difficult thing to estimate is the amount of fabric I used, because there are so many layers in some of the pieces. So I have assumed 10metres of fabric at £5 per metre.

Lesson learnt for the next module - keep a careful note of materials used.



No comments:

Post a Comment